title: "Type C compression-sleeve repairs on the Oasis Pipeline, Texas"
description: "Vendor account of 22 Type C compression sleeves installed in service on a 36-inch Texas gas line for SCC and DSAW seam defects."
section: case-studies
updated: 2026-11-25
canonical: https://pipelinerepairs.com/case-studies/cs-06-type-c-compression-sleeve-repairs-on-the-oasis-pipeline-texa/
markdown: https://pipelinerepairs.com/articles/case-studies/cs-06-type-c-compression-sleeve-repairs-on-the-oasis-pipeline-texa.md
---

# Type C compression-sleeve repairs on the Oasis Pipeline, Texas

In short. Vendor account of 22 Type C compression sleeves installed in service on a 36-inch Texas gas line for SCC and DSAW seam defects.

Source: T.D. Williamson (2025). Account type: Vendor account.

TDW's case study describes SCC and DSAW defects at 13 locations on a 36-inch Texas pipeline running at about 820 psig. The company installed 22 PETROSLEEVE Type C compression sleeves (36-inch by 1-inch A516-70 shells, 36 inches long) in four days, using three crews, while the line remained in service. TDW contrasts that schedule with a conventional Type B sleeve campaign that it says could have taken up to five weeks. The account is vendor marketing, but it is a concrete, recent public example of compression-sleeve use on cracking and seam-weld defects.

## Method

TDW PETROSLEEVE Type C (compression) steel sleeves. Two half-shells are compressed onto the carrier pipe over epoxy; sidebars are welded to the sleeve, not to the carrier pipe.

## Defect

Stress-corrosion cracking (SCC) and double-submerged-arc-weld (DSAW) defects at 13 sites

## Pipe

36-inch pipeline operating at about 820 psig, Texas (Oasis Pipeline / Southeast Texas system feeding the Houston market, per TDW). Sleeves: NPS 36 x 1-inch thick x 36-inch long, ASTM A516-70.

## Outcome

TDW reports 22 sleeves installed in four days with three welding crews, and says this was about a 90 percent time reduction versus a Type B sleeve campaign that might have taken up to five weeks. The line stayed in service. No safety incidents were reported by the vendor. These time and safety claims are the manufacturer's.

Schedule, cost, and service-life figures in this note are the publisher’s claims. They were not checked against an operator record or a laboratory report.

Dates: Official case-study page does not state the installation year. TDW posted the case on LinkedIn on 21 November 2025.

Maker named in the source: T.D. Williamson (PETROSLEEVE).

## Sources

- [PETROSLEEVE Type C compression-sleeve repairs on the Oasis Pipeline, Texas](https://www.tdwilliamson.com/petrosleevecasestudy) — T.D. Williamson
- [Related public record](https://www.linkedin.com/posts/tdw_rapid-pipeline-integrity-restoration-on-the-activity-7397732028974039040-_tKN) — T.D. Williamson