title: "ROV-installed leak-sealing clamp on a 10-inch water-injection riser flange, Foinaven field"
description: "Deepwater ROV-installed clamp with seabed-mixed resin injection to seal a 10-inch water-injection flange leak at 500 meters."
section: case-studies
updated: 2026-11-25
canonical: https://pipelinerepairs.com/case-studies/cs-10-rov-installed-leak-sealing-clamp-on-a-10-inch-water-injection-riser-flan/
markdown: https://pipelinerepairs.com/articles/case-studies/cs-10-rov-installed-leak-sealing-clamp-on-a-10-inch-water-injection-riser-flan.md
---

# ROV-installed leak-sealing clamp on a 10-inch water-injection riser flange, Foinaven field

In short. Deepwater ROV-installed clamp with seabed-mixed resin injection to seal a 10-inch water-injection flange leak at 500 meters.

Source: Furmanite, working with Subsea 7, for BP; reported by Rigzone. Account type: Trade press.

A 10-inch flange on the Foinaven water-injection riser termination was leaking at 500 metres, west of Shetland, and seawater at the joint was a threat to injection and therefore to oil production. Furmanite designed a compact clamp that an ROV could set without heavy lift gear, and developed a two-part resin that could be mixed and injected on the seabed so it would not cure in the hose on the way down. After surface tests on a flooded spool, Subsea 7's ROV installed the clamp, injected the compound, and Furmanite reported a seal in about 24 hours, with water injection maintained. This is a trade-press account of a vendor job, but it includes unusual technical detail on deepwater ROV injection.

## Method

Bespoke Furmanite clamp, about 666 x 680 x 140 mm and 200 kg, installed and resin-injected entirely by ROV, including a remotely mixed sealing compound

## Defect

Leaking 10-inch seabed flange joint on the flowline termination assembly at the base of a water-injection riser; seawater ingress and corrosion at the joint

## Pipe

10-inch flange, 500 metres water depth, Foinaven field, west of Shetland. Operating pressure not stated.

## Outcome

BP's senior subsea engineer is quoted as saying the leak was affecting production and that the team wanted to avoid a shutdown. Furmanite reports the clamp was installed and injected, and the joint sealed, in about 24 hours including cure, allowing water injection and oil production to continue at capacity.

This account is taken from a public regulatory or investigative record.

Dates: Publication year is not clearly stated on the Rigzone page (the URL contains a placeholder date).

Maker named in the source: Furmanite (later part of TEAM).