title: "Composite sleeve repair of 900 feet of cooling-tower corrosion on a U.S. refinery pipeline"
description: "Installation of 903 pre-cured composite sleeves along 900 feet of corroded 8-inch U.S. refinery piping while remaining in service."
section: case-studies
updated: 2026-11-25
canonical: https://pipelinerepairs.com/case-studies/cs-12-composite-sleeve-repair-of-900-feet-of-cooling-tower-corrosion-on-a-u-s-refi/
markdown: https://pipelinerepairs.com/articles/case-studies/cs-12-composite-sleeve-repair-of-900-feet-of-cooling-tower-corrosion-on-a-u-s-refi.md
---

# Composite sleeve repair of 900 feet of cooling-tower corrosion on a U.S. refinery pipeline

In short. Installation of 903 pre-cured composite sleeves along 900 feet of corroded 8-inch U.S. refinery piping while remaining in service.

Source: CSNRI / Critica Infrastructure (Clock Spring). Account type: Vendor account.

A U.S. refinery found corrosion along 900 feet of an 8-inch aboveground line running beside a cooling tower, caused by airborne drift. Welding would have been difficult because other product lines were as close as 3 inches and the damaged line had to stay in service. CSNRI-trained crews installed 903 pre-cured composite sleeves, including on 45- and 90-degree fittings, finishing in about three weeks at 75 to 100 feet per day. The write-up is vendor marketing, but it is a clearly described, large-scale composite repair in tight plant piping.

## Method

Clock Spring pretensioned e-glass composite sleeves (903 units), including on 45-degree and 90-degree fittings, installed while the line remained in service

## Defect

External corrosion from airborne cooling-tower drift along about 900 feet (274 m) of aboveground pipe

## Pipe

8-inch (203 mm) pipe, air/gas mixture, United States refinery. Grade and operating pressure not stated.

## Outcome

CSNRI reports 903 units were installed over three weeks at roughly 75 to 100 feet per day, with no hot work, and that nearby process lines (as close as 3 inches) stayed in service. The vendor describes the repair as providing at least 50 years of corrosion protection. That service-life claim is the manufacturer's.

Schedule, cost, and service-life figures in this note are the publisher’s claims. They were not checked against an operator record or a laboratory report.

Dates: Year of the repair is not stated on the current case-study page. A 2004 conference paper by Clock Spring describes a closely matching 12-inch, 900-foot cooling-tower corrosion job; the current page lists 8-inch pipe. Treat the official page as the source and do not merge the two pipe sizes.

Maker named in the source: CSNRI (Clock Spring).

## Sources

- [Clock Spring repair of 900 feet of cooling-tower corrosion on a U.S. refinery pipeline](https://www.cs-nri.com/case_study/clock-spring-provides-permanent-repair-to-damaged-refinery-pipeline/) — CSNRI / Critica Infrastructure (Clock Spring)