# High-pressure CO2 mid-line isolation and bypass for piggability upgrades, Cortez Pipeline

In short. In-service split-tee welding, hot taps, and a dual-seal mid-line isolation with a 24-inch bypass on a 30-inch CO2 line operating at 2,140 psi, so launchers and valves could be added without a shutdown.

Source: STATS Group vendor case study and PDF, with a 2016 World Pipelines report of the same job. Account type: Vendor account, corroborated in a trade article.

Kinder Morgan needed to add full-bore inline valves and pigging launchers and receivers on the Cortez Pipeline, a 500-mile, 30-inch carbon dioxide line running from southwestern Colorado to Denver City, without taking the line out of service. The line was being converted from a non-piggable system to a piggable one. Operating pressure is given as 2,140 psi (148 bar). At that pressure and ambient temperature the carbon dioxide is in the supercritical state; when it is vented to atmosphere it flashes to vapour, the temperature falls sharply, and solid carbon dioxide can form if the vent is not controlled.

The vendor's account of the work is as follows. While the line stayed in service, the site contractor excavated the pipe and welded on split-tee fittings using qualified in-service welding procedures. Two 30-inch fittings gave access for mid-line isolation tools, and two 24-inch fittings served a bypass. High-pressure slab valves were installed, leak-tested, and used for hot taps, with the coupons recovered. A 24-inch bypass was installed, purged, and leak-tested, then placed in service. Isolation tools with two independently testable seals were then deployed through a single full-bore hot-tap opening at each end of the work section, set into the flowing line, and used to divert flow through the bypass. The isolated section was vented in a controlled way. Each seal was pressure-tested with full line pressure in the expected direction, and the annulus between the seals was vented and monitored as a zero-energy zone before an isolation certificate was issued.

The vendor says the main engineering problem was the carbon dioxide phase change. Solid carbon dioxide, or a very low temperature, could block the passages used to monitor the seal annulus or affect the seals and steel. The published account describes controlling the blowdown rate to keep temperature above the design limits of the seals and the steel, and using nitrogen to purge carbon dioxide from the seal annulus so the annulus pressure could be lowered without forming a solid phase.

The publisher reports isolations at four sites along the line, at around 2,000 psi, and more than 160 days of isolation time, with no reported seal degradation or leaks past the primary barrier, after which the tools were unset and recovered and the slab valves closed. Those figures, and the claim that this was the first leak-tight double-block-and-bleed isolation of a high-pressure carbon dioxide pipeline, are the publisher's.

Schedule, cost, and service-life figures in this note are the publisher's claims. They were not checked against an operator record or a laboratory report.

Dates: The World Pipelines report was published 26 August 2016. The dates of the individual site interventions are not stated on the pages opened for this note.

Maker named in the source: STATS Group. The source uses the vendor's trademarked name BISEP for the dual-seal isolation tool deployed through a single hot-tap opening, and SureTap for the hot-tap machine.

## Sources

- [30" Dual BISEP, Cortez Pipeline, New Mexico, USA](https://www.statsgroup.com/resources/case-studies/30-dual-biseps-cortez-pipeline-new-mexico-usa) — STATS Group
- [World First: Leak-Tight Double Block and Bleed Isolation on High Pressure CO2 Pipelines (PDF)](https://f.hubspotusercontent10.net/hubfs/7717268/StatsGroup_August2020/docs/world-first-leak-tight-double-block-and-bleed-isolation-on-high-pressure-c02-pipelines.pdf) — STATS Group
- [Breaking new ground on Cortez pipeline project](https://www.worldpipelines.com/project-news/26082016/Breaking-new-ground-on-Cortez-pipeline-project/) — World Pipelines