# British Columbia: Pipeline Regulation and BC Energy Regulator requirements

In short. The Energy Resource Activities Act and Pipeline Regulation as they apply to repair, what the BC Energy Regulator's Operations Manual requires for a pipeline repair notice, and its integrity management program protocol.

The BC Energy Regulator (BCER) regulates pipelines within British Columbia under the Energy Resource Activities Act and its regulations. It reports regulating more than 50,000 km of oil and gas pipelines, most of them gathering lines in the northeast. Pipelines that cross out of the province are under federal jurisdiction, and the BCER keeps a role in reviewing applications and issuing provincial authorizations for them. See [who regulates what in Canada](/regulations/canada-pipeline-regulators-overview/).

## Pipeline Regulation (B.C. Reg. 281/2010)

The Pipeline Regulation is made under the Energy Resource Activities Act. The BC Laws consolidation checked for this page is current to 17 November 2026 and shows the last amendment as B.C. Reg. 26/2025, effective 1 April 2025. The BCER's legislative framework page notes that its own consolidation is unofficial and that operators are responsible for checking the rules that apply to them.

- **Standards (section 3).** A pipeline permit holder must not design, construct, operate, maintain, deactivate, reactivate, or abandon its pipeline except in accordance with CSA Z662 and Annex A of Z662, where those apply to the substance transported or an engineering assessment shows them appropriate. Otherwise approved alternative codes or standards that provide equal or greater safety apply. The Regulation defines CSA Z662 "as amended from time to time." See [CSA Z662](/codes/csa-z662/).
- **Integrity management (section 7).** A permit holder must prepare a pipeline integrity management program before constructing or operating, and the program must comply with CSA Z662 and Annex N of Z662. A permit holder must not construct, operate, maintain, repair, deactivate, or abandon the pipeline unless that work is done in accordance with the program. On an official's request the holder must make the program available to the regulator.
- **Work near other infrastructure (section 4).** Before beginning construction, maintenance, or repair along, over, or under a public place, highway, road, railway, underground communication or power line, or another pipeline, the holder must give notice to the owner or responsible authority at least 5 days in advance unless a different time is agreed. In an emergency the work may begin immediately after notice is given.
- **Venting (section 7.1).** The Regulation limits venting of natural gas when depressuring a pipeline, with an exception where an imminent risk to health, safety, or the environment must be addressed.

## Operations Manual: repairs and notices of intent

Chapter 11 of the BCER's Energy Resource Activity Operations Manual (version 2.2, published August 2026) gives operating guidance for permitted pipeline activity. It restates that permit holders must follow the current CSA Z662 including Annexes A and N as required by section 3 of the Pipeline Regulation, and it says permit holders are required to perform pipeline repairs as per CSA Z662.

The manual's "NOI: Pipeline Repair" covers:

- pipe replacements or cut-out repairs where the repair is under 50 metres long, is not associated with a water crossing, and does not result in higher stress in the replaced section as a percentage of SMYS at MOP; and
- application of repair sleeves, including composite or weld-on sleeves.

The notice is due within 30 days after completing field work. The BCER expects detail: a description of the action (for example, application of a composite sleeve or a cut-out repair); attachments describing the scope of work, whether the repair is temporary or permanent, material specifications and their suitability, timelines, and the affected pipeline project numbers and segments; how replacement pipe will be pressure tested or the results if it was pretested; how the work will be executed (flaring, purging, plugging, and so on); the drivers for the repair; and diagrams showing the affected portions. Submissions are reviewed and accepted if the information is sufficient.

Three further points from the manual's "Items of Note":

- **Temporary repairs** require, in addition, an engineering assessment under CSA Z662 Clause 10.12.
- **Grind repairs.** No NOI is required where defects were removed by grinding.
- **Recoating.** Inspection work that removes and reapplies the external coating does not need an NOI.

After an incident, the manual says a holder can file an NOI to repair or replace in-kind with the same material specification, or a pipeline amendment where the replacement is not in-kind. The manual also asks for 48 hours' notice by email before pressure testing an existing pipeline when no amendment or NOI applies, with an engineering assessment as required by Clause 10.3.9 of CSA Z662.

## Integrity management program protocol

The BCER says pipeline integrity management programs have been a regulatory requirement since 1999. It publishes a Compliance Assurance Protocol for pipeline integrity management programs, effective 4 December 2023, that sets out how it checks programs and guides permit holders in developing one that meets section 7 of the Pipeline Regulation and CSA Z662. A self-assessment questionnaire for pipeline operators is also available.

## Using this with other Canadian sources

The BCER's repair notice is an administrative step on top of the standard. The technical content of a repair, including defect evaluation and repair method limits, comes from Z662 Clause 10. The federal equivalents are in [CER Onshore Pipeline Regulations](/regulations/cer-onshore-pipeline-regulations/), and Alberta's are in [Alberta Pipeline Rules](/regulations/alberta-pipeline-rules-and-aer/).

## Sources

- [Pipeline Regulation, B.C. Reg. 281/2010 (consolidation current to 17 November 2026)](https://www.bclaws.gov.bc.ca/civix/document/id/complete/statreg/281_2010) — BC Laws, King's Printer
- [Legislative Framework](https://www.bc-er.ca/how-we-regulate/legislative-framework/) — BC Energy Regulator
- [Energy Resource Activity Operations Manual, 11. Pipeline Activity (version 2.2, August 2026)](https://www.bc-er.ca/files/operations-documentation/Energy-Resource-Activity-Operations-Manual/ERAOM-Chapter-11.pdf) — BC Energy Regulator
- [Integrity Management Program (IMP)](https://www.bc-er.ca/energy-professionals/operations-documentation/integrity-management-program-imp/) — BC Energy Regulator
- [Compliance Assurance Protocol, Integrity Management Programs for Pipeline Systems](https://www.bc-er.ca/files/operations-documentation/Integrity-Management-Program-Compliance-Assurance/Pipeline-IMPs-Documentation/Pipelines-IMP-Compliance-Assurance-Protocol.pdf) — BC Energy Regulator
- [Pipelines (BC Energy Regulator)](https://www.bc-er.ca/what-we-regulate/oil-gas/pipelines/) — BC Energy Regulator