# Saskatchewan and Ontario: provincial pipeline requirements

In short. How Saskatchewan's Pipelines Act, 1998, licensing regulations, and Directive PNG034 apply CSA Z662 to pipeline repair, and what Ontario's oil and gas pipeline systems regulation provides, with links to the official sources.

Pipelines that stay inside one province are regulated by that province, and the provinces differ in who the regulator is and how much of the technical content they take from CSA Z662. [Alberta](/regulations/alberta-pipeline-rules-and-aer/) and [British Columbia](/regulations/bc-pipeline-regulation-and-bcer/) have their own pages. This page covers Saskatchewan and Ontario, the two other provinces whose official sources were read for this site. For the federal regulator, see [CER Onshore Pipeline Regulations](/regulations/cer-onshore-pipeline-regulations/), and for the overall split see [who regulates what in Canada](/regulations/canada-pipeline-regulators-overview/).

## Saskatchewan

The Government of Saskatchewan's pipeline licensing page lists three documents as the legal authority to regulate design, construction, operation, discontinuation, and abandonment of oil, natural gas, and other pipelines in accordance with the latest edition of CSA Z662:

- The Pipelines Act, 1998.
- The Pipelines Administration and Licensing Regulations (PALR).
- Directive PNG034, Saskatchewan Pipelines Code.

Chapter 5 of PNG034 sets application requirements. The page also describes licensing through the province's Integrated Resource Information System (IRIS), where applications are classed as routine or non-routine depending on whether risk rules are triggered, and a Pipeline Safety and Loss Management System Audit. The deadline to retroactively license designated pipelines passed on 20 January 2024, and the ministry says an unlicensed designated pipeline may be subject to administrative penalties.

### Which edition of Z662 applies

Bulletin BT2023-009, issued 30 June 2023 by the Energy Regulation Division, records how Saskatchewan treats new editions. Under section 2.1 of PNG034, the minimum requirements for the design, construction, operation, modification, discontinuation, and abandonment of pipelines must be in accordance with the most recent published version of CSA Z662. When the ninth edition (Z662-23) was published on 30 June 2023, the Division said it intended to prohibit the safety-class system and the pressure-design approach introduced in Annex C, and would not enforce those elements. The bulletin names only those Annex C elements. See [CSA Z662](/codes/csa-z662/) for how the clauses are organized.

## Ontario

Ontario Regulation 210/01, *Oil and Gas Pipeline Systems*, is made under the Technical Standards and Safety Act, 2000. It is the province's licensing regulation for oil and gas pipeline systems. The e-Laws record checked for this page was current to 23 November 2026. Section 18(6) provides that an inspector may inspect the installations and repairs performed by or on behalf of a licence applicant or holder, and the workmanship relating to them, to determine whether they comply with the Regulation, so repair work is within the scope of provincial inspection. The Regulation defines an "Oil and Gas Pipeline Systems Code Adoption Document," adopted under Ontario Regulation 223/01, and uses a list of authorized standards; consult those documents for the editions in force, because this page does not summarize them.

## Other provinces

Other provinces have their own pipeline statutes and regulators, and this site adds a page for a province only after reading its official source. Until then, the federal and provincial split on the [overview page](/regulations/canada-pipeline-regulators-overview/) shows where to start, and the regulator's own website is the place to confirm the current edition of any rule.

## Sources

- [Pipeline Licensing](https://www.saskatchewan.ca/business/agriculture-natural-resources-and-industry/oil-and-gas/oil-and-gas-licensing-operations-and-requirements/pipeline-licensing) — Government of Saskatchewan