FAQ
Questions that come up first
What is this site?
Pipeline Repairs is a practical engineering reference for people who specify, review, or study pipeline repairs. It summarizes public regulations, public research, and widely published engineering methods.
Can I use a page or a calculator as the basis for a repair decision?
No. The site is information, not engineering advice and not a compliance determination. A repair decision has to be made by a qualified person under the operator’s procedures, the governing regulations, and the edition of any standard those regulations incorporate. The calculators omit tool tolerance, corrosion growth, interaction, and material uncertainty.
Why don’t the code pages quote ASME, API, ISO, or AMPP?
Those documents are copyrighted. The pages name the document, describe its role in plain language, and link to the publisher. Federal regulations and Federal Register notices are public, so the regulation pages paraphrase those and link to the official text.
Which edition of a standard applies on a regulated pipeline?
The edition incorporated by reference in 49 CFR 192.7 or 195.3, not automatically the newest edition on the publisher’s shelf. A newer edition can still be useful engineering. It is not the legal edition until the incorporation section says so.
What is the difference between original B31G and Modified B31G?
Original B31G uses a parabolic area (two-thirds of the rectangle), a flow stress of 1.1 times SMYS, and a simple Folias factor that the method drops once L²/(Dt) exceeds 20. Modified B31G uses an area factor of 0.85, a flow stress of SMYS plus 10,000 psi, and a closer Folias approximation that remains defined for longer defects. RSTRENG is a third method: it integrates the actual depth profile. The calculator on this site runs only the first two.
Does the design-pressure calculator return MAOP?
No. It returns hoop stress and, if you ask for it, the design pressure from §192.105 or the internal design pressure from §195.106. Gas MAOP is set under Subpart L and can be limited by test pressure, class location, and operating history. Liquid MOP has its own rules in Part 195.
Can a composite wrap be a permanent repair of a leak?
Do not assume so. Section 192.717’s prescriptive list for permanent leak repair does not name composite wrap. A performance-based alternative exists only where tests and analyses show the method permanently restores serviceability, and the operator’s own procedure allows it. Enforcement cases and ASME B31.8 practice have rejected composite wrap as a permanent leak repair. Composite systems are built and qualified as reinforcement of a non-leaking, prepared defect.
Did PHMSA ban Type A sleeves in 2026?
No. Advisory Bulletin ADB-2026-02 (91 FR 3780, 28 January 2026) tells hazardous-liquid operators that Type A sleeves can hide corrosion, shield cathodic protection, and crack under pressure cycling if they are poorly installed or poorly managed. It does not prohibit the repair. Advisory bulletins do not create new rules.
What is the Mega Rule?
A nickname, not a citation. The relevant final rules are the 1 October 2019 gas transmission rule on MAOP reconfirmation and assessments (84 FR 52180) and the 24 August 2022 rule on repair criteria, integrity management, cathodic protection, and management of change (87 FR 52224). A January 2025 correction removed three provisions the D.C. Circuit vacated. A July 2026 notice is a proposal, not a final rule.
What happens if metal loss is deeper than 80 percent of the wall?
Treat it as a repair, not as a calculation exercise. The B31G methods were not meant to accept defects that deep, because leak risk and measurement error dominate. Metal loss greater than 80 percent of nominal wall is an immediate repair condition for both gas transmission (§§192.714 and 192.933) and hazardous-liquid integrity management (§195.452).
Which units should I use?
Either U.S. customary (inches, psi) or SI (millimetres, MPa). The calculators convert to inches and psi before applying the code expressions, then convert results back. The regulatory text itself is written in both in many sections. Do not mix a millimetre depth with an inch wall in the same submission.
Are the case studies real?
Yes. Entries under Case studies are documented repairs or in-service failures, each tied to a public source or a named publisher’s field account. Invented walk-throughs are in Worked examples and are labeled “Example only.” Public PHMSA orders are in Enforcement and incidents, starting with CPF 4-2026-025-CAO. NTSB reports stay in the regulations note on San Bruno and Marshall.
How do I correct an error?
The contact page can store a topic request or an email for notes about new reference material. It is not an engineering consultation and it does not deliver a mailbox reply. Where this site and the eCFR disagree, follow the eCFR.
How is a new article added?
Add a Markdown file under src/content/articles with the frontmatter described in the README, including at least one public source URL. The section index, sitemap, and search index pick it up on the next build. Do not paste copyrighted standard text.
How do the gas and liquid repair schedules differ?
Gas transmission uses immediate, timed, and monitored lists: the timed list is one year inside a high consequence area (§192.933) and two years outside one (§192.714), with remaining-strength thresholds written as multiples of MAOP that depend on class location. Hazardous-liquid integrity management (§195.452(h)) uses immediate, 60-day, and 180-day lists with thresholds written against maximum operating pressure, and it has no equivalent of the gas §192.712(c) strain-analysis exception for dents. See the side-by-side note under Regulations.
Is ASME PCC-2 or ISO 24817 incorporated by reference in the federal pipeline rules?
No. Neither appears in the incorporation lists in §192.7 or §195.3. On a gas transmission line the legal test for a composite repair is §192.713: a method that reliable engineering tests and analyses show can permanently restore serviceability. PCC-2 Part 4 and ISO 24817 are the usual way operators show that, and PHMSA- and BSEE-sponsored guidance recommends using only systems qualified to one of them.
When is a coating survey required after a repair?
Under §192.461(f), on onshore steel gas transmission lines, when a repair or replacement results in 1,000 feet or more of backfill length. The DCVG, ACVG, or comparable survey must be done promptly and no later than 6 months after backfill. Severe damage (DCVG voltage drop above 60 percent or ACVG above 70 dBµV) must be repaired within 6 months of the assessment, or within 6 months of receiving permits. Part 195 has no equivalent requirement.
Can a dent be cleared by analysis instead of repaired?
On gas transmission, several dent conditions in §192.714 and §192.933 can be moved to the monitored list if an engineering critical assessment under §192.712(c) shows critical strain is not exceeded. The ECA has eleven required elements, including FEA strain, a fatigue life with a safety factor of 5 or more using multiple models, and advance notice to PHMSA. Dents deeper than 10 percent of OD, or with strain above the lesser of 10 percent or critical strain, cannot be cleared. The liquid rules have no equivalent exception.
Can a defective girth weld be repaired while the line is in service?
On gas transmission, §192.715(b) allows an in-service weld repair only if the weld is not leaking, pressure is reduced so hoop stress is no more than 20 percent of SMYS, and grinding leaves at least 1/8 inch of weld thickness. Otherwise the weld is repaired out of service under §192.245 or with a full-encirclement welded split sleeve of appropriate design. Because girth-weld flaws are loaded axially, a hoop-only repair such as a Type A sleeve does not reinforce them.
Who is allowed to make a hot tap?
Section 192.627 requires every tap on a gas pipeline under pressure to be performed by a crew qualified to make hot taps. Welds must follow a procedure qualified under §192.225 or §195.214 (API 1104 Appendix B is the in-service route), welders must meet §192.227 and §192.229 or §195.222, and the operator qualification rules in Part 192 Subpart N and Part 195 Subpart G apply to the covered tasks.