CPF 4-2026-025-CAO: Sterling Heights sleeve failure

In short PHMSA’s 21 September 2026 corrective action order on Energy Transfer’s Marysville–Toledo crude line, a failed Type B sleeve on 1967 LF-ERW pipe, and the related Twin Oaks Type A sleeve release.

Updated . Sources are listed at the end. Markdown version.

On 21 September 2026 PHMSA issued Corrective Action Order CPF 4-2026-025-CAO to Energy Transfer, LP. The order concerns a crude-oil release discovered on 18 September 2026 in Sterling Heights, Macomb County, Michigan, on the Marysville–Toledo Crude pipeline. PHMSA states that the release came from a failed Type B repair sleeve on 1967 low-frequency electric-resistance-welded pipe, and that Energy Transfer could not produce the original repair records for that sleeve or for hundreds of other sleeves on its hazardous-liquid systems. The findings in the order are preliminary. The cause of the failure is stated as still unknown. The PDF is the record.

The order was signed by Paul Roberti, Administrator, and served under 49 CFR 190.5. It was issued under 49 U.S.C. 60112 without prior notice, with a right to request a hearing within 10 days. It does not replace Parts 190 through 199.

What the order says happened

The Marysville–Toledo Crude pipeline is part of Energy Transfer’s Sunoco Products West system. The order describes it as about 130 miles of crude-oil line from Marysville, Michigan, to Toledo, Ohio, with three pump stations and six breakout tanks. About 109.7 miles pass through high consequence areas under §195.450. The line is monitored by a computational pipeline monitoring system. The pipe is stated as 16-inch, 0.281-inch wall, grade X52, coal-tar coated, manufactured in 1967 with LF-ERW seams. Why that vintage of seam is treated as a known integrity threat is on the LF-ERW note.

On 18 September 2026 a member of the public reported crude oil seeping from the ground at a commercial intersection near a residential development and flowing into a storm drain. The local fire department reported the spill to the National Response Center at 11:37 a.m. Eastern Time and also notified Energy Transfer. Energy Transfer reported the spill at 1:52 p.m. and estimated 15 barrels. It isolated about 16 miles between Utica Station and 11 Mile Station.

On 19 September, after excavations along the right-of-way, Energy Transfer confirmed the release at a Type B sleeve. The order’s visual observation is that the sleeve was leaking through two holes in its longitudinal weld. The carrier at that location is inside a 20-inch steel casing and coated in concrete. The sleeve was not coated. It sat in a cut-out of the casing, and crude oil appeared to be moving through the sleeve and down the casing. Energy Transfer indicated the sleeve was installed in 2010. It could not locate the original repair records for the defect under that sleeve, or records sufficient to verify the installation or ongoing integrity of eleven other steel repair sleeves on the same line.

The line had remained shut in since 18 September. A PHMSA investigator was on site later that day. Energy Transfer had recovered at least 15 barrels from the failure location and the storm drain. The failure location is a high consequence area. Energy Transfer was removing the failed sleeve and had staged pretested pipe, and had said it intended to return the line to service after the new pipe was installed. The order does not treat that intention as authorization to restart.

The Twin Oaks sleeve, January 2025

The order pairs Sterling Heights with an earlier release on the Twin Oaks Pipeline in Upper Makefield Township, Pennsylvania. Twin Oaks is described as a 14-inch products line, carrying jet fuel, diesel, and gasoline, from the Twin Oaks Terminal in Aston, Pennsylvania, to the Newark Terminal in Newark, New Jersey. Sun Pipe Line Company, a predecessor of Sunoco, installed it in 1956. Between 1987 and 1999 Sunoco installed 45 Type A sleeves on it.

On 31 January 2025, after odor complaints over several months, Sunoco excavated a Type A sleeve in a high consequence area in a residential neighborhood. The excavation found a failure under the sleeve. Petroleum products had contaminated soil and several drinking-water wells. Energy Transfer could not locate the original repair records for that sleeve or for four other Type A sleeves on Twin Oaks.

On 13 February 2025 PHMSA issued a Notice of Proposed Safety Order, CPF 4-2025-054-NOPSO, alleging that the Type A sleeves on Twin Oaks created an unacceptable integrity risk. On 2 May 2025 a consent order in that case required, among other things, a failure-history evaluation, an evaluation of leak detection, removal and metallurgical analysis of certain Type A sleeves, and a root-cause analysis. The Twin Oaks investigation is described as still open. The case page is CPF 4-2025-054-NOPSO. What a Type A sleeve does and does not contain is on the Type A note. The pressure-containing sleeve that leaked in Sterling Heights is a Type B sleeve.

Records PHMSA says were missing

After Upper Makefield, PHMSA sent requests for information on 18 April 2025 and 17 April 2026 covering sleeves on other hazardous-liquid systems. The order lists the operator identification numbers those requests used: OPID 18718 (Sunoco), OPID 32099 (Energy Transfer), OPID 7063 (Harbor), OPID 22442 (West Texas Gulf), and OPID 32683 (Inland Corp), with the mileage and states stated in the order. Responses were submitted on 17 June, 17 July, and 15 August 2025, and 14 July 2026.

PHMSA’s reading of those responses is that sleeves with characteristics similar to the Twin Oaks sleeve are installed on other Energy Transfer hazardous-liquid lines in New Jersey, Pennsylvania, Ohio, Michigan, and Texas, and that Energy Transfer could not locate original repair records, or records otherwise sufficient to verify installation and ongoing integrity, for steel encirclement sleeves on those systems. That gap includes the Type B sleeve at Sterling Heights.

The order states what those records should contain if they are to verify a sleeve: the description, location, and assessment of the defect under the sleeve; the remediation, including grinding and recoating; and the installation, including fit-up to the carrier and, for a pressure-containing Type B sleeve, the welding procedure and test reports. It points at §195.404(c)(1), which requires repair records for the useful life of the pipe, and §195.214(b), which requires retention of welding procedures and qualification tests. The separate note on repair records is where those duties are set out without the facts of this order mixed in.

The order also states two limits that do not depend on this operator. Magnetic-flux-leakage tools generally cannot assess metal loss under a steel sleeve. A sleeve that is not tight to the carrier can hold water, shield cathodic protection, and corrode the pipe underneath. Both points are why a missing record is not a paperwork gap that an in-line inspection run automatically fills.

Why PHMSA issued the order now

Section 60112 lets PHMSA order corrective action, including a shutdown or a pressure restriction, when a facility is or would be hazardous and delay would risk serious harm. The order says the cause is still unknown, that the failure was on vintage LF-ERW pipe, and that failures under at least two sleeves, each with signs of improper installation, indicate a likelihood of further failures. It also says the leak-detection systems did not find either the Marysville–Toledo release or the Twin Oaks release, that thousands of miles of these systems pass through high consequence areas, and that the absence of sleeve records means the integrity of the prior repairs cannot be determined. On that basis PHMSA determined that continued operation of the defined segments without the corrective measures would be hazardous, and that the order had to be issued before a hearing.

What the order requires

The order defines four pieces of pipe, and they are not the same length.

  • Failure. The leak discovered on 18 September 2026 near Sterling Heights.
  • Isolated Segment. The roughly 16 miles from Utica Station to 11 Mile Station. It may not operate until the Director of the Southwest Region, or a designee, authorizes it.
  • Affected Segment. The roughly 130-mile Marysville-to-Toledo line.
  • Affected Pipelines. Any hazardous-liquid pipeline facility owned or operated by Energy Transfer, its subsidiaries, and related entities. Later sleeve items use this definition, not the 16-mile piece.

The required actions, in the order’s numbering:

  1. Keep the Isolated Segment shut down until the Director authorizes operation.
  2. Hold a 20 percent pressure reduction on the entire Affected Segment, so operating pressure does not exceed 80 percent of the actual operating pressure at 11:37 a.m. Eastern Time on 18 September 2026. The restriction stays until the Director approves an increase. Within 10 days, report the pressures and the reduced set-points at each pump or compressor station and each mainline regulating station. Alarms, control points, and mechanical overpressure devices have to match. The monthly review has to account for in-line-inspection anomalies and be sent to the Director.
  3. Submit a written restart plan for the Isolated Segment, and do not restart until the Director has approved the whole plan. The plan has to include daylight restart, advance notice to local emergency officials, ground patrol during restart, pressure increases held for at least two hours each, a review of construction, operations, and integrity records for conditions like the failure, and a management-of-change record.
  4. After that approval, the Isolated Segment may return to service only at or below the 80 percent restriction.
  5. The Director may lift or change the restriction on a written showing that a higher pressure is safe for the known defects.
  6. The Director may allow a temporary change if mitigative and preventive measures are in place. An appeal of that decision goes to the Associate Administrator for Pipeline Safety.
  7. Within 45 days, complete mechanical and metallurgical testing and failure analysis of the failed pipe, including soil and foreign material, by an independent laboratory the Director approves. The testing protocol and the laboratory are due within 10 days. Chain of custody is required. Draft and final reports go to the Director when they go to Energy Transfer.
  8. Within 90 days, complete a root-cause failure analysis by a different independent third party. The scope and protocol are due within 30 days. Weekly calls with PHMSA continue until the report is submitted. The report has to say whether the findings apply elsewhere on the system.
  9. Within 15 days, verify records for the Affected Segment to confirm maximum operating pressure, as discussed in Advisory Bulletin ADB-2012-06, and send the documentation to the Director.
  10. Within 60 days after the root-cause report is approved, submit a remedial work plan for the Affected Segment. It has to identify similar pipe, assemble the failure history, integrate the new tests with existing assessment data, and set repair criteria and a schedule. Approved plans are incorporated into the order.
  11. Within 90 days, inventory every steel encirclement repair sleeve on the Affected Pipelines. If the operator cannot tell whether a sleeve is Type A or Type B, the order says to list it as Type A. For each sleeve the inventory has to give, or mark as unknown: installation date; type of defect repaired; material, including age, grade, length, thickness, coating, wrap, and whether epoxy was used; method of end sealing; fit-up measurements; whether operator or contractor personnel installed it; and the procedure used.
  12. Within 30 days, review prior in-line-inspection results on the Affected Pipelines, including vendor raw data from the past 10 calendar years, and look for conditions like the two failures. Documentation is due within 45 days.
  13. Within 120 days, submit a plan to evaluate the integrity of each steel encirclement sleeve on the Affected Pipelines. Sleeves whose integrity cannot reasonably be assured have to be removed. A sleeve that stays needs a technical justification and additional integrity measures.
  14. Within 120 days, submit a sleeve remediation plan for the Affected Pipelines, covering both failures. It has to identify similar pipe, integrate the two failure analyses with existing data, and specify assessments that can address the causes, including tools that can actually detect the anomalies, hydrostatic testing, close-interval and cathodic-protection surveys, coating surveys, stress-corrosion-cracking surveys, and selective-seam-corrosion surveys where those threats apply.
  15. An independent third party approved by the Director has to facilitate the core of that sleeve plan.
  16. Keep a single documentation report that will be submitted in full when the order’s items are done, so the Director can review closure.
  17. Submit quarterly progress reports. The first is due 1 November 2026.
  18. PHMSA requests, and does not phrase as a mandate, that costs of procedures, physical changes, and environmental remediation be tracked in those quarterly reports.

The Director may approve submissions in part, approve them with conditions, modify them, or send them back. Extensions require a timely written request and good cause. Material sent in response can be made public. The order says PHMSA may add measures later, with notice and a hearing where that is consistent with safety.

What this note is not

This is not a finding that every Type B sleeve, or every 1967 LF-ERW joint, will fail. The order says the metallurgy and the root cause are still to be done. It is not an instruction to remove sleeves that this site has not seen. Numbers in a later slide — barrels, miles, counts of sleeves — should be checked against the PDF, because an amended order or a final report can supersede a preliminary paragraph. The case file is CPF 4-2026-025-CAO. The PDF linked above is the 21 September 2026 order.

Sources

  1. Corrective Action Order CPF 4-2026-025-CAO, 21 September 2026 (PDF) — PHMSA
  2. Enforcement case CPF 4-2026-025-CAO — PHMSA
  3. Notice of Proposed Safety Order CPF 4-2025-054-NOPSO — PHMSA
  4. PHMSA enforcement data — PHMSA
  5. 49 U.S.C. 60112 — U.S. Code