01 · Repair methods

Cut-out and replacement

In short Why removing a cylinder of pipe is the reference permanent repair, and what the replacement pipe and the tie-in welds still have to satisfy.

Updated . Sources are listed at the end. Markdown version.

Cutting out a cylinder and welding in sound pipe removes the defect instead of reinforcing it. PHMSA’s fact sheet calls replacement the alternative the industry standards prefer when it is practical, and notes that many operators replace weld-to-weld rather than insert a short pup, accepting more excavation in exchange for fewer girth welds. Section 192.713(a)(1) names that cut-out first. Section 192.717(a) names it first for leaks. Section 192.714 requires a listed condition either to be removed by a cylinder that restores MAOP using §192.105 and the class-location design factors, or to be repaired by a method shown to restore that MAOP another way.

Replacement is the reference because the arguments that follow a sleeve — Did the filler fill the dent? Can the tool see under the steel? Is the crack still growing? — do not apply to a piece of pipe that is no longer there. The arguments that replace them are ordinary construction arguments, and they are not small.

The new pipe has to be a known pipe

The replacement is designed for the MAOP or MOP the line will operate at, with a wall, grade, and seam that the design formula can use. On gas transmission lines, repairs under §§192.714 and 192.933 have to use properties documented in traceable, verifiable, and complete records. If those records do not exist, §192.607 is how missing properties are obtained, and §192.712 states the conservative assumptions that apply until they are. A pup of unknown grade, even a thick one, is how a system ends up with a joint that nobody can put into an MAOP file. The San Bruno rupture, NTSB/PAR-11/01, is the public investigation that made incomplete pipe records a national regulatory subject. It was not a failed sleeve. It was a seam in a pup that the integrity program did not know.

The tie-in welds are new girth welds. They are made under the operator’s welding procedure, by qualified welders, and examined the way that procedure and the construction rules require. Whether a short replacement must be pressure tested in place, or may be a pre-tested pup with nondestructive examination of the tie-ins, depends on the testing subpart that applies to that hoop stress and that location (Part 192 Subpart J, or the Part 195 testing rules). This page will not collapse that into a rule of thumb. Read the subpart for the line in front of you.

When a cut-out is the decision, not the preference

Some features are poor candidates for reinforcement even when reinforcement is legally available:

  • Through-wall cracks, or crack fields whose length and toughness are not in hand.
  • Seam defects in vintage low-frequency or direct-current ERW, electric-flash-welded, or other low joint-factor seams, where the repair criterion is aimed at the seam itself.
  • Damage that has wrinkled or buckled the pipe, so the geometry is no longer a pipe a sleeve can sit on.
  • Any case in which the pressure cannot be made safe for in-service welding and a mechanical clamp is outside the defect the rule allows.
  • A defect so long that the sleeve or wrap would itself become a buried object nobody can assess.

The cost of a cut-out is excavation, outage or a bypass, two or more girth welds, and coating of the new pipe and the joints. The cost of not cutting out is a repair whose permanence has to be re-argued at every later assessment. Section 192.933 requires the operator to be able to show that the remediation will hold until the next reassessment. A cylinder of known pipe is the simplest way to make that showing. It is not always the available way. Hot tapping and plugging exist for the case where the line cannot be taken out of service to do the cut-out; they do not change what the replacement pipe has to be.

Sources

  1. PHMSA fact sheet: Pipeline repairs — PHMSA
  2. 49 CFR 192.713 — eCFR
  3. 49 CFR 192.714 — eCFR
  4. 49 CFR 192.717 — eCFR
  5. 49 CFR 192.105 — eCFR
  6. 49 CFR 192.607 — Verification of pipeline material properties — eCFR
  7. NTSB/PAR-11/01, San Bruno — NTSB