Part 195 repair and integrity duties

In short Hazardous-liquid repair, corrosion remediation, and the integrity-management response schedule that still differs from the gas rules.

Updated . Sources are listed at the end. Markdown version.

Part 195 regulates hazardous liquid and carbon dioxide pipelines. The vocabulary is maximum operating pressure, not MAOP. Internal design pressure for steel pipe is §195.106: P = (2St/D) × E × F. The design factor is 0.72 except where the section requires a lower factor. There is no temperature derating multiplier in the formula.

Section 195.401 is the general operations duty, including repairing the line in a reasonable time once an operator finds it unsafe. Section 195.422 is the repair section: safe, timely, and made so as to prevent damage to people, property, or the environment. It does not list Type A sleeves or composite wraps. A method that cannot be defended under that sentence is not saved by being common.

Corrosion

Section 195.585 is the corroded-pipe remedy: replace, repair, or reduce pressure, with remaining strength determined by a method in §195.587. Those methods track the gas list — B31G and RSTRENG and equivalents — and the integrity rule repeats them. Cathodic-protection adequacy is judged under §195.571, which points at the criteria in Part 192 Appendix D.

Integrity-management response, still the early-2000s schedule

Section 195.452 is the hazardous-liquid integrity rule for segments that could affect a high consequence area. Paragraph (h) is the response schedule. It has not been rebuilt the way the gas schedule was in 2022. As PHMSA restated it in the July 2026 proposal, immediate conditions include metal loss greater than 80 percent of nominal wall, a remaining-strength calculation showing predicted burst pressure less than MOP, and top-side dents that have metal loss, cracking, or a stress riser or that exceed 6 percent of the diameter. The sixty-day list includes bottom-side dents with those interacting features. The 180-day list includes a crack confirmed by excavation, general corrosion over 50 percent of the wall, metal loss over 50 percent at crossings or girth welds or in widespread circumferential corrosion, corrosion of or along a longitudinal seam, a gouge or groove deeper than 12.5 percent of the wall, and several dent-depth cases.

Interpretation PI-17-0014 (26 April 2018) treated corrosion along a longitudinal seam as a 180-day condition without a special exception for the corrosion mechanism; PHMSA withdrew that letter on 12 September 2025 and pointed to FAQ 7.16, which treats the 180-day criterion as covering corrosive attack that specifically affects the seam, not automatically every pit near one. Interpretation PI-24-0003 holds that an operator who classified anomalies more conservatively than the minimum rule, and wrote that classification into its program, has to follow the program.

Immediate conditions come with a pressure reduction or a shutdown until the repair is done. The rule tells the operator how to calculate the reduction and, if no suitable remaining-strength method exists, requires at least a 20 percent reduction from recent operating pressure.

The July 2026 NPRM would replace much of this structure with failure-pressure ratios, a one-year “near-term” tier, and a new §195.453, and would extend material-verification ideas from Part 192 into Part 195. None of that is current text. The docket is PHMSA-2025-0019. Until a final rule is effective, paragraph (h) of §195.452 is the schedule, and API RP 1160 is the program practice the section already requires in the incorporated edition.

Section 195.404(c)(1) keeps the date, location, and description of each repair to pipe for the useful life of the pipe. For a steel sleeve, that description has to be enough to know what defect was covered and how the sleeve was installed. The repair records note is that duty. Paragraph (c)(1)(i) of §195.452 separately requires a seam-capable assessment on low-frequency ERW pipe susceptible to longitudinal seam failure. That seam is the subject of the LF-ERW note.

Sources

  1. 49 CFR 195.106 — eCFR
  2. 49 CFR 195.401 — eCFR
  3. 49 CFR 195.422 — eCFR
  4. 49 CFR 195.452 — eCFR
  5. 49 CFR 195.571 — eCFR
  6. 49 CFR 195.585 — eCFR
  7. 49 CFR 195.587 — eCFR
  8. PI-17-0014 — PHMSA
  9. Hazardous liquid integrity management FAQs, 12 September 2025 revision (FAQ 7.16) — PHMSA
  10. PI-24-0003 — PHMSA
  11. 2026 repair-criteria NPRM — Federal Register