03 · Regulations and official guidance
Repair schedules: gas transmission versus hazardous liquid
In short Side by side, the response clocks in §192.714, §192.933, and §195.452(h): what is immediate, what is one year, two years, 60 days, or 180 days, and how pressure must be reduced while a repair is pending.
The gas and liquid rules sort anomalies into buckets with deadlines, but the buckets are not the same. Gas transmission has three lists (immediate, a timed list, monitored) and two clocks for the timed list: one year inside a high consequence area under §192.933(d) and two years outside under §192.714(d). Hazardous liquid integrity management under §195.452(h)(4) has immediate, 60-day, and 180-day lists, and thresholds that are written against maximum operating pressure rather than multiples of it. The text below is current eCFR language as of November 2026. The 2026 repair-criteria proposal would change parts of both and is not yet law.
When the clock starts
Both parts count from discovery, not from the inspection run. Discovery is when the operator has adequate information to know a condition threatens integrity. The operator has to get that information promptly and no later than 180 days after the assessment, or notify PHMSA with the reason and an expected date. That 180-day rule is in §192.933(b) for gas HCAs and §195.452(h)(2) for liquid lines.
Which section applies
| Pipeline | Section |
|---|---|
| Gas transmission in an HCA | §192.933 |
| Onshore gas transmission outside an HCA (not alternative MAOP) | §192.714 |
| Gas gathering and offshore lines | §192.711(b)(1)(i): permanent repair “as soon as feasible” |
| Hazardous liquid, could affect an HCA | §195.452(h) |
| Hazardous liquid, not covered by IM | §195.401(b): correct within a reasonable time, and do not operate a segment with a condition that presents an immediate hazard until it is corrected |
Section 192.711(a) also requires temporary measures on steel transmission lines operating at or above 40 percent of SMYS whenever a permanent repair is not feasible at discovery. The temporary-versus-permanent question is separate from the schedule and is covered in Temporary and permanent repairs.
Immediate conditions
| Condition | Gas (§192.714(d)(1), §192.933(d)(1)) | Liquid (§195.452(h)(4)(i)) |
|---|---|---|
| Metal loss depth | Greater than 80% of nominal wall | Greater than 80% of nominal wall |
| Remaining strength | Predicted failure pressure ≤ 1.1 × MAOP | Predicted burst pressure < MOP |
| Top dent with metal loss, cracking, or a stress riser | Immediate, unless a §192.712(c) analysis shows critical strain is not exceeded | Immediate |
| Top dent by depth alone | Not on the immediate list | Greater than 6% of diameter |
| Seam metal loss | On DC-ERW, LF-ERW, EFW, or a joint factor below 1.0, with failure pressure < 1.25 × MAOP | Not on the immediate list (corrosion along a seam is a 180-day condition) |
| Cracks | Crack depth plus metal loss > 50% of wall, or greater than the tool’s maximum measurable depth | Not on the immediate list (a confirmed crack is a 180-day condition) |
| Evaluator judgment | Yes | Yes |
“Top” means between the 8 o’clock and 4 o’clock positions in the gas text (the upper two-thirds) and “above the 4 and 8 o’clock positions” in the liquid text.
Timed conditions
Gas, one year in an HCA and two years outside one. The same items appear in both lists:
- A smooth top dent deeper than 6% of diameter (0.50 inch below NPS 12), unless a §192.712(c) analysis shows critical strain is not exceeded.
- A dent deeper than 2% of diameter (0.250 inch below NPS 12) that affects curvature at a girth weld or a longitudinal or helical seam, with the same analysis exception.
- A bottom dent (4 to 8 o’clock) with metal loss, cracking, or a stress riser, with the same exception.
- Metal loss with predicted failure pressure below 1.39 × MAOP in Class 2 or below 1.50 × MAOP in Class 3 and 4. In Class 1, metal loss above 1.1 × MAOP follows the ASME B31.8S section 7 schedule figure.
- Metal loss at a crossing of another pipeline, in widespread circumferential corrosion, or that could affect a girth weld, below 1.39 × MAOP in Class 1 (and uprated Class 1 pipe in Class 2) or 1.50 × MAOP elsewhere.
- Seam-preferential metal loss on ERW, EFW, or joint-factor-below-1.0 seams, and cracks or crack-like anomalies, below the same 1.39 or 1.50 thresholds (failure pressure under §192.712(d)).
Liquid, 60 days. A top dent deeper than 3% of diameter (0.250 inch below NPS 12), and a bottom dent with any metal loss, cracking, or stress riser.
Liquid, 180 days. A dent deeper than 2% (0.250 inch below NPS 12) affecting curvature at a girth or long seam weld; a top dent deeper than 2%; a bottom dent deeper than 6%; remaining strength showing an operating pressure below current MOP; general corrosion predicted deeper than 50%; predicted metal loss deeper than 50% at a crossing, in widespread circumferential corrosion, or where it could affect a girth weld; a potential crack confirmed as a crack once excavated; corrosion of or along a longitudinal seam; and a gouge or groove deeper than 12.5% of nominal wall. Appendix C of Part 195 lists other conditions an operator should evaluate.
Gas, monitored. Dents above the depth triggers that a §192.712(c) analysis has cleared go on a monitored list and are re-examined at later assessments. See Dent engineering critical assessment.
Pressure while the repair is pending
Gas. For an immediate condition, or when the operator cannot meet a timed deadline, §192.714(e) and §192.933(a) require reducing pressure to one of three levels: no more than 80% of the operating pressure at discovery; no more than predicted failure pressure times the class-location design factor; or no more than predicted failure pressure divided by 1.1. If the schedule cannot be met and a pressure reduction cannot provide safety, the operator notifies PHMSA under §192.18. A reduction that lasts more than 365 days also needs a §192.18 notice with a technical justification. Outside HCAs, the calculations and the reduced pressure must be kept for 5 years after the repair.
Liquid. For an immediate condition the operator reduces pressure or shuts down. The reduction is calculated from the remaining-strength method. If no suitable method can be identified, the reduction is at least 20% of the actual operating pressure for the two months before the inspection date. A reduction longer than 365 days is reported under §195.452(m) with the reasons and further remedial action.
What does not carry across
- Gas thresholds scale with class location. Liquid thresholds compare against MOP directly.
- Gas allows a §192.712(c) strain analysis to move some dents off the immediate and timed lists. The liquid text has no equivalent exception.
- Liquid has a stand-alone depth trigger for top dents (6% immediate, 3% at 60 days, 2% at 180 days). Gas puts a smooth top dent on the timed list only above 6%.
- “Repair within” and “schedule evaluation and remediation within” are different verbs. The gas lists say repair or remediate. The liquid 60-day and 180-day lists say schedule evaluation and remediation.
For the methods that produce the predicted failure pressure, see Corrosion and metal loss and ASME B31G, Modified B31G, and RSTRENG.
Sources
- 49 CFR 192.714, transmission lines outside HCAs: permanent field repair — eCFR
- 49 CFR 192.933, remediation in high consequence areas — eCFR
- 49 CFR 195.452, hazardous liquid integrity management, paragraph (h) — eCFR
- 49 CFR 192.711, transmission lines: general requirements for repair procedures — eCFR
- 49 CFR 195.401, general requirements (non-IM repair timing) — eCFR
- 49 CFR Part 195, Appendix C — eCFR
- 2026 NPRM, Repair Criteria for Hazardous Liquid and Gas Transmission Pipelines, 91 FR 42272 — Federal Register
Related notes
- Corrosion metal loss — Defect assessment
- Dents — Defect assessment
- Dent engineering critical assessment — Defect assessment
- Cracks and crack-like defects — Defect assessment
- ASME B31G, Modified B31G, and RSTRENG — Codes and standards
- Choosing a repair — Repair methods
Also in Regulations and official guidance
- How to read PHMSA sources
- Part 192 repair and integrity duties
- Part 195 repair and integrity duties
- Gas transmission rule updates
- Official repair guidance
- Advisory bulletins that bear on repair
- Interpretations and FAQs
- PHMSA research on repair methods
- Lessons from public investigations
- Repair records for sleeves and other repairs
- Temporary and permanent repairs
- AB-539: engineered composite alterations in Alberta
- Pipeline regulation in Canada: who regulates what
- CER Onshore Pipeline Regulations and pipeline repair
- CER safety and information advisories that bear on repair
- Alberta: Pipeline Act, Pipeline Rules, and AER Directive 077
- British Columbia: Pipeline Regulation and BC Energy Regulator requirements
- Saskatchewan and Ontario: provincial pipeline requirements
- TSB pipeline investigation reports: what Canada's safety board publishes
Spotted an error? Engineers keep this site honest.Report an error or suggest a correction