03 · Regulations and official guidance
Gas transmission rule updates
In short What the 2019 and 2022 final rules actually changed, what the 2025 court correction removed, and what the July 2026 proposal is not.
“Mega Rule” is industry shorthand for a gas transmission rulemaking that was too large to finish in one document. Citing it as if it were a section number will not survive a conversation with a regulator. The documents are these.
1 October 2019 — MAOP reconfirmation and assessments
The final rule at 84 FR 52180 requires operators of certain onshore steel transmission segments to reconfirm MAOP where records are not traceable, verifiable, and complete, including previously untested “grandfathered” segments operating at or above 30 percent of SMYS in specified locations. Section 192.624 is the operative section. Methods include a pressure test, a pressure reduction, and an engineering critical assessment under §192.632, among others. The rule also expanded assessment requirements beyond high consequence areas into moderate consequence areas for pipe that can be inspected with in-line tools, and it set the material-property verification process in §192.607 that later repair analyses depend on. Completion dates in §192.624 run to 2028 for half the mileage and 2035 for the rest, with a narrow extension process. Those dates are in the section; confirm them there before planning around a secondary summary.
24 August 2022 — repair criteria
The final rule at 87 FR 52224 added repair criteria for onshore transmission pipe that is not already covered by Subpart O, strengthened integrity-management repair criteria, and dealt with cathodic protection, management of change, and extreme weather. Section 192.714 is the non-HCA repair section. Section 192.933 is the HCA section. Section 192.712 is where predicted failure pressure, dent strain, and crack analysis are specified. The repair has to restore MAOP using documented properties, or the conservative defaults, and the timing rules distinguish immediate conditions from conditions that follow the B31.8S figure or a one-year or two-year schedule.
15 January 2025 — what the court removed
The D.C. Circuit vacated three pieces of the 2022 rule. PHMSA’s correction, Federal Register document 2025-00073 (90 FR 3713), takes them out of the code: monitoring of internal corrosive constituents at §192.478; the immediate crack criterion at a predicted failure pressure below 1.25 times MAOP; and the inclusion of high-frequency ERW seams in the immediate preferential-metal-loss criterion. The rest of the 2022 repair framework stayed. A memo that still quotes the 1.25 crack trigger is quoting a dead provision.
8 July 2026 — a proposal
Docket PHMSA-2025-0019, 91 FR 42272, proposes to finish the move toward failure-pressure ratios and to extend that approach to hazardous liquid lines. For gas, the preamble describes the changes as adding an immediate crack criterion at a ratio of 1.1, raising the immediate crack-depth threshold from 50 percent to 70 percent, lowering the immediate seam-corrosion ratio from 1.25 to 1.1, and narrowing the interacting-dent criterion so ordinary corrosion under 10 percent of the wall is not treated like mechanical damage. For liquids, the proposal would replace the 60- and 180-day tiers with a one-year near-term tier and would add failure-pressure criteria next to the old depth criteria. It would also rewrite dent engineering-critical-assessment provisions that the court had remanded, and it would name additional metal-loss and crack models.
The comment period ended 8 September 2026. As of the review date on this article, the proposal is not a final rule. Check the docket before treating any of those numbers as a duty. The pages on Part 192 and Part 195 describe the rules that are in the eCFR.
Sources
- Final rule, 1 October 2019, 84 FR 52180 — Federal Register
- 49 CFR 192.624 — MAOP reconfirmation — eCFR
- Final rule, 24 August 2022, 87 FR 52224 — Federal Register
- Corrections, 15 January 2025 — Federal Register
- NPRM, 8 July 2026, 91 FR 42272 — Federal Register
- Regulations.gov docket PHMSA-2025-0019 — Regulations.gov
Related notes
- Cracks and crack-like defects — Defect assessment
- Corrosion metal loss — Defect assessment
- ASME B31.8 and B31.8S — Codes and standards
- Choosing a repair — Repair methods
- How codes and regulations differ — Codes and standards
- Type A sleeve leak on the Twin Oaks Pipeline, Upper Makefield Township, Pennsylvania — Case studies
Also in Regulations and official guidance
- How to read PHMSA sources
- Part 192 repair and integrity duties
- Part 195 repair and integrity duties
- Official repair guidance
- Advisory bulletins that bear on repair
- Interpretations and FAQs
- PHMSA research on repair methods
- Lessons from public investigations
- Repair records for sleeves and other repairs
- Temporary and permanent repairs
- AB-539: engineered composite alterations in Alberta
- Repair schedules: gas transmission versus hazardous liquid
- Pipeline regulation in Canada: who regulates what
- CER Onshore Pipeline Regulations and pipeline repair
- CER safety and information advisories that bear on repair
- Alberta: Pipeline Act, Pipeline Rules, and AER Directive 077
- British Columbia: Pipeline Regulation and BC Energy Regulator requirements
- Saskatchewan and Ontario: provincial pipeline requirements
- TSB pipeline investigation reports: what Canada's safety board publishes
Spotted an error? Engineers keep this site honest.Report an error or suggest a correction