Composite sleeve repair of 900 feet of cooling-tower corrosion on a U.S. refinery pipeline

In short Installation of 903 pre-cured composite sleeves along 900 feet of corroded 8-inch U.S. refinery piping while remaining in service.

Updated . Sources are listed at the end. Markdown version.

Source: CSNRI / Critica Infrastructure (Clock Spring). Account type: Vendor account.

A U.S. refinery found corrosion along 900 feet of an 8-inch aboveground line running beside a cooling tower, caused by airborne drift. Welding would have been difficult because other product lines were as close as 3 inches and the damaged line had to stay in service. CSNRI-trained crews installed 903 pre-cured composite sleeves, including on 45- and 90-degree fittings, finishing in about three weeks at 75 to 100 feet per day. The write-up is vendor marketing, but it is a clearly described, large-scale composite repair in tight plant piping.

Method

Clock Spring pretensioned e-glass composite sleeves (903 units), including on 45-degree and 90-degree fittings, installed while the line remained in service

Defect

External corrosion from airborne cooling-tower drift along about 900 feet (274 m) of aboveground pipe

Pipe

8-inch (203 mm) pipe, air/gas mixture, United States refinery. Grade and operating pressure not stated.

Outcome

CSNRI reports 903 units were installed over three weeks at roughly 75 to 100 feet per day, with no hot work, and that nearby process lines (as close as 3 inches) stayed in service. The vendor describes the repair as providing at least 50 years of corrosion protection. That service-life claim is the manufacturer’s.

Schedule, cost, and service-life figures in this note are the publisher’s claims. They were not checked against an operator record or a laboratory report.

Dates: Year of the repair is not stated on the current case-study page. A 2004 conference paper by Clock Spring describes a closely matching 12-inch, 900-foot cooling-tower corrosion job; the current page lists 8-inch pipe. Treat the official page as the source and do not merge the two pipe sizes.

Maker named in the source: CSNRI (Clock Spring).

Sources

  1. Clock Spring repair of 900 feet of cooling-tower corrosion on a U.S. refinery pipeline — CSNRI / Critica Infrastructure (Clock Spring)