07 · Case studies
Composite sleeve repair of 900 feet of cooling-tower corrosion on a U.S. refinery pipeline
In short Installation of 903 pre-cured composite sleeves along 900 feet of corroded 8-inch U.S. refinery piping while remaining in service.
Source: CSNRI / Critica Infrastructure (Clock Spring). Account type: Vendor account.
A U.S. refinery found corrosion along 900 feet of an 8-inch aboveground line running beside a cooling tower, caused by airborne drift. Welding would have been difficult because other product lines were as close as 3 inches and the damaged line had to stay in service. CSNRI-trained crews installed 903 pre-cured composite sleeves, including on 45- and 90-degree fittings, finishing in about three weeks at 75 to 100 feet per day. The write-up is vendor marketing, but it is a clearly described, large-scale composite repair in tight plant piping.
Method
Clock Spring pretensioned e-glass composite sleeves (903 units), including on 45-degree and 90-degree fittings, installed while the line remained in service
Defect
External corrosion from airborne cooling-tower drift along about 900 feet (274 m) of aboveground pipe
Pipe
8-inch (203 mm) pipe, air/gas mixture, United States refinery. Grade and operating pressure not stated.
Outcome
CSNRI reports 903 units were installed over three weeks at roughly 75 to 100 feet per day, with no hot work, and that nearby process lines (as close as 3 inches) stayed in service. The vendor describes the repair as providing at least 50 years of corrosion protection. That service-life claim is the manufacturer’s.
Schedule, cost, and service-life figures in this note are the publisher’s claims. They were not checked against an operator record or a laboratory report.
Dates: Year of the repair is not stated on the current case-study page. A 2004 conference paper by Clock Spring describes a closely matching 12-inch, 900-foot cooling-tower corrosion job; the current page lists 8-inch pipe. Treat the official page as the source and do not merge the two pipe sizes.
Maker named in the source: CSNRI (Clock Spring).
Sources
- Clock Spring repair of 900 feet of cooling-tower corrosion on a U.S. refinery pipeline — CSNRI / Critica Infrastructure (Clock Spring)
Related notes
- Composite wraps — Repair methods
- ASME PCC-2 — Codes and standards
- ISO 24817 — Codes and standards
- Corrosion metal loss — Defect assessment
- AB-539: engineered composite alterations in Alberta — Regulations and official guidance
- Choosing a repair — Repair methods
Also in Case studies
- Type A sleeve leak on the Twin Oaks Pipeline, Upper Makefield Township, Pennsylvania
- Type B sleeve leak on the Marysville-Toledo Crude Pipeline, Sterling Heights, Michigan (CAO 4-2026-025)
- Type A sleeve leak on Colonial Line 1, Huntersville, North Carolina (CPF 2-2021-005-NOPSO)
- Type A sleeve leak on Colonial Line, Gwinnett County (Harbins Road), Georgia
- Type A sleeve leak on the CNG/Plantation pipeline, Belton, South Carolina
- Type C compression-sleeve repairs on the Oasis Pipeline, Texas
- In-service X70 Type B sleeve installation on West-East Gas Pipeline Line 3, China
- Subsea Clamp+Sleeve repair of a buckled 10-inch crude line, South Marsh Island Block 59
- ROV-installed Flange Repair Split+Sleeve on a 10-inch water-injection line, offshore Angola
- ROV-installed leak-sealing clamp on a 10-inch water-injection riser flange, Foinaven field
- Emergency leak repair on a 30-inch onshore pipeline with a bolt-on fitting
- Composite sleeve repair of a dent and seam-weld crack on a 24-inch crude-oil pipeline
- Underwater composite sleeve repair of girth-weld corrosion on a 12-inch gas pipeline
- Composite sleeve repair of a rockfall dent on a 36-inch hydroelectric pipeline in the French Alps
- Burst test of a composite sleeve repair recovered after 25 years in service (installed 1995)
- Composite pipe-wrap repairs of corrosion on Equistar Pipeline, Texas
- Weld-wrap composite reinforcement of an internal weld defect on a 24-inch products pipeline, Western Europe
- Composite repair of a 32-inch offshore riser, Thailand
- Splash-zone composite repair of mechanical damage on a 12-inch subsea crude line, Gulf of Mexico
- Carbon-fiber repair of a deep crack on a 900 mm gas-transmission bend
- Epoxy-filled sleeve encapsulation of a large dent on a 14-inch trunkline, Papua New Guinea
- High-pressure line-plug isolation to remove a stuck pig and replace a leaking valve on a CO2 pipeline
- Line-plug train isolation and diversion of two 24-inch gas transmission lines under a planned Singapore subway station
- Line-plug train isolation to decommission a gas-processing plant off a 36-inch transmission line, Alabama
- Emergency double line-plug isolation of a burning 14-inch NGL pipeline after a third-party strike, West Texas
- 12-inch double line-plug isolation with bypass for a live gas-line repair, Oklahoma
- Line stop to connect 8-inch PE gas mains, St. Louis
- Insertion valves and line stops after a sheared 8-inch valve, Covington, Ohio
- Epoxy recoating of HDD-damaged girth and spiral welds, Kansas
- West Virginia 30-inch leak at a previous composite wrap
- Port Allen valve-station dent reinforced with an E-glass wrap
- 14-inch diesel line at Redding, Pennsylvania, carbon wrap
- Hinged protective tools on a 24-inch Florida line during bridge work
- Custom Type B sleeve around an existing clamp, Florida
- Type B sleeves replacing mechanical clamps at a Texas refinery
- Double-hump girth-weld sleeve on a 26-inch Kentucky gas line
- Compression sleeve on a crude line, Middle East operator
Spotted an error? Engineers keep this site honest.Report an error or suggest a correction