07 · Case studies

12-inch double line-plug isolation with bypass for a live gas-line repair, Oklahoma

In short Live 12-inch double line-plug line stop with full-size bypass maintaining downstream gas delivery during an Oklahoma pipeline repair.

Updated . Sources are listed at the end. Markdown version.

Source: T.D. Williamson, via a 5 February 2020 LinkedIn post by Nancy Karrer (2020). Account type: Vendor account.

A February 2020 LinkedIn post by a TDW employee describes a 12-inch double line-plug isolation with a 12-inch bypass for a long-standing Oklahoma gas customer. The work was done on a cold winter day so that repairs could be made on an isolated segment while gas kept moving downstream. The post is short and does not describe the defect, pressure, or duration, but it is a public, dated example of a standard onshore HT&P repair isolation.

Method

12-inch double line-plug isolation with a 12-inch bypass, allowing repairs on the isolated segment while gas continued downstream

Defect

Not stated; described only as repairs made during a hot-tapping and plugging job for an Oklahoma customer

Pipe

12-inch natural-gas pipeline, Oklahoma, on a cold winter day. Pressure and grade not stated.

Outcome

The post says gas continued to flow to customers while the isolated section was repaired. No further technical results are given.

Schedule, cost, and service-life figures in this note are the publisher’s claims. They were not checked against an operator record or a laboratory report.

Dates: LinkedIn post dated 5 February 2020.

Maker named in the source: T.D. Williamson. The source uses the vendor’s trademarked name STOPPLE® for its line-plugging equipment.

Sources

  1. 12-inch double STOPPLE® isolation with bypass for a live gas-line repair, Oklahoma — T.D. Williamson, via a 5 February 2020 LinkedIn post by Nancy Karrer

Also in Case studies

Spotted an error? Engineers keep this site honest.Report an error or suggest a correction

Open the form on this page

Occasional updates