Subsea isolation and permanent bypass after anchor damage on an 8-inch condensate line, Gulf of Thailand

In short Divers installed mechanical hot-tap clamps on a live 8-inch gas-condensate line at 60 m water depth, hot-tapped it, set a dual-seal isolation, and commissioned a permanent seabed bypass around pipe dragged by an anchor.

Updated . Sources are listed at the end. Markdown version.

Source: STATS Group. Account type: Vendor account.

A section of an 8-inch gas-condensate export pipeline in the Gulf of Thailand had been dragged about 8 metres from its original position by a vessel anchor and needed a permanent repair. The line was live, in about 60 metres of water, at pressures the vendor gives as 7 to 21 bar. The operator and the installation contractor, CUEL Ltd, required the damaged pipe to be isolated and removed without shutting in production and without putting divers on an unisolated line.

The vendor’s account, completed in December 2016, is as follows. Six permanent 8-inch mechanical hot-tap clamps with 8-inch branched offtakes were installed by saturation divers at three locations. At each location one clamp was the tie-in for a new bypass and the other was the entry for a dual-seal isolation tool. After the clamps were bolted up, the annulus and body flange were pressure-tested at 56 bar. A hot-tap machine then cut the coupon from the pressurised pipe; the coupon was recovered, inspected, and measured. An 8-inch bypass spool was installed on the seabed and the clamp valves were opened so flow could enter the bypass as well as the original line.

Isolation tools with primary and secondary seals were then deployed through full-bore hot-tap openings in the clamps, set hydraulically from the vessel, and seal-tested to a double-block-and-bleed isolation. The vendor says an isolation certificate was issued and renewed every 12 hours. The isolated damaged section was flushed back into the export line, depressurised to the subsea ambient pressure of 6 bar, and cut with diamond-wire cutters. Abandonment plugs were set in the open ends of the damaged pipe for wet storage. Permanent mechanical connectors with blind flanges were fitted to the remaining pipe ends and annulus-tested at 56 bar. The isolation tools were then unset and recovered, completion plugs were set in the clamp flanges and pressure-tested, the slab valves were removed, and blind flanges were installed as a second barrier.

The onshore programme included a representative test on actual pipe sections and training of the vessel dive team on the subsea hot-tap machine before the six offshore taps.

Schedule, cost, and service-life figures in this note are the publisher’s claims. They were not checked against an operator record or a laboratory report.

Dates: The vendor states the repair was completed in December 2016.

Maker named in the source: STATS Group. The source uses the vendor’s trademarked name BISEP for the dual-seal isolation tool deployed through a single hot-tap opening.

Sources

  1. 8" Subsea Pipeline Isolation & Repair, Gulf of Thailand — STATS Group

Also in Case studies

Spotted an error? Engineers keep this site honest.Report an error or suggest a correction

Open the form on this page

Occasional updates