07 · Case studies
High-pressure CO2 mid-line isolation and bypass for piggability upgrades, Cortez Pipeline
In short In-service split-tee welding, hot taps, and a dual-seal mid-line isolation with a 24-inch bypass on a 30-inch CO2 line operating at 2,140 psi, so launchers and valves could be added without a shutdown.
Source: STATS Group vendor case study and PDF, with a 2016 World Pipelines report of the same job. Account type: Vendor account, corroborated in a trade article.
Kinder Morgan needed to add full-bore inline valves and pigging launchers and receivers on the Cortez Pipeline, a 500-mile, 30-inch carbon dioxide line running from southwestern Colorado to Denver City, without taking the line out of service. The line was being converted from a non-piggable system to a piggable one. Operating pressure is given as 2,140 psi (148 bar). At that pressure and ambient temperature the carbon dioxide is in the supercritical state; when it is vented to atmosphere it flashes to vapour, the temperature falls sharply, and solid carbon dioxide can form if the vent is not controlled.
The vendor’s account of the work is as follows. While the line stayed in service, the site contractor excavated the pipe and welded on split-tee fittings using qualified in-service welding procedures. Two 30-inch fittings gave access for mid-line isolation tools, and two 24-inch fittings served a bypass. High-pressure slab valves were installed, leak-tested, and used for hot taps, with the coupons recovered. A 24-inch bypass was installed, purged, and leak-tested, then placed in service. Isolation tools with two independently testable seals were then deployed through a single full-bore hot-tap opening at each end of the work section, set into the flowing line, and used to divert flow through the bypass. The isolated section was vented in a controlled way. Each seal was pressure-tested with full line pressure in the expected direction, and the annulus between the seals was vented and monitored as a zero-energy zone before an isolation certificate was issued.
The vendor says the main engineering problem was the carbon dioxide phase change. Solid carbon dioxide, or a very low temperature, could block the passages used to monitor the seal annulus or affect the seals and steel. The published account describes controlling the blowdown rate to keep temperature above the design limits of the seals and the steel, and using nitrogen to purge carbon dioxide from the seal annulus so the annulus pressure could be lowered without forming a solid phase.
The publisher reports isolations at four sites along the line, at around 2,000 psi, and more than 160 days of isolation time, with no reported seal degradation or leaks past the primary barrier, after which the tools were unset and recovered and the slab valves closed. Those figures, and the claim that this was the first leak-tight double-block-and-bleed isolation of a high-pressure carbon dioxide pipeline, are the publisher’s.
Schedule, cost, and service-life figures in this note are the publisher’s claims. They were not checked against an operator record or a laboratory report.
Dates: The World Pipelines report was published 26 August 2016. The dates of the individual site interventions are not stated on the pages opened for this note.
Maker named in the source: STATS Group. The source uses the vendor’s trademarked name BISEP for the dual-seal isolation tool deployed through a single hot-tap opening, and SureTap for the hot-tap machine.
Sources
Related notes
- Hot tapping and line plugging — Repair methods
- In-service welding and hydrogen pipelines — Repair methods
- Cut-out and replacement — Repair methods
- ASME B31.8 and B31.8S — Codes and standards
- Part 192 repair and integrity duties — Regulations and official guidance
- Choosing a repair — Repair methods
Also in Case studies
- Type A sleeve leak on the Twin Oaks Pipeline, Upper Makefield Township, Pennsylvania
- Type B sleeve leak on the Marysville-Toledo Crude Pipeline, Sterling Heights, Michigan (CAO 4-2026-025)
- Type A sleeve leak on Colonial Line 1, Huntersville, North Carolina (CPF 2-2021-005-NOPSO)
- Type A sleeve leak on Colonial Line, Gwinnett County (Harbins Road), Georgia
- Type A sleeve leak on the CNG/Plantation pipeline, Belton, South Carolina
- Type C compression-sleeve repairs on the Oasis Pipeline, Texas
- In-service X70 Type B sleeve installation on West-East Gas Pipeline Line 3, China
- Subsea Clamp+Sleeve repair of a buckled 10-inch crude line, South Marsh Island Block 59
- ROV-installed Flange Repair Split+Sleeve on a 10-inch water-injection line, offshore Angola
- ROV-installed leak-sealing clamp on a 10-inch water-injection riser flange, Foinaven field
- Emergency leak repair on a 30-inch onshore pipeline with a bolt-on fitting
- Composite sleeve repair of 900 feet of cooling-tower corrosion on a U.S. refinery pipeline
- Composite sleeve repair of a dent and seam-weld crack on a 24-inch crude-oil pipeline
- Underwater composite sleeve repair of girth-weld corrosion on a 12-inch gas pipeline
- Composite sleeve repair of a rockfall dent on a 36-inch hydroelectric pipeline in the French Alps
- Burst test of a composite sleeve repair recovered after 25 years in service (installed 1995)
- Composite pipe-wrap repairs of corrosion on Equistar Pipeline, Texas
- Weld-wrap composite reinforcement of an internal weld defect on a 24-inch products pipeline, Western Europe
- Composite repair of a 32-inch offshore riser, Thailand
- Splash-zone composite repair of mechanical damage on a 12-inch subsea crude line, Gulf of Mexico
- Carbon-fiber repair of a deep crack on a 900 mm gas-transmission bend
- Epoxy-filled sleeve encapsulation of a large dent on a 14-inch trunkline, Papua New Guinea
- High-pressure line-plug isolation to remove a stuck pig and replace a leaking valve on a CO2 pipeline
- Line-plug train isolation and diversion of two 24-inch gas transmission lines under a planned Singapore subway station
- Line-plug train isolation to decommission a gas-processing plant off a 36-inch transmission line, Alabama
- Emergency double line-plug isolation of a burning 14-inch NGL pipeline after a third-party strike, West Texas
- 12-inch double line-plug isolation with bypass for a live gas-line repair, Oklahoma
- Line stop to connect 8-inch PE gas mains, St. Louis
- Insertion valves and line stops after a sheared 8-inch valve, Covington, Ohio
- Epoxy recoating of HDD-damaged girth and spiral welds, Kansas
- West Virginia 30-inch leak at a previous composite repair
- Port Allen valve-station dent reinforced with an E-glass composite repair
- 14-inch diesel line at Redding, Pennsylvania, carbon-fiber composite repair
- Hinged protective tools on a 24-inch Florida line during bridge work
- Custom Type B sleeve around an existing clamp, Florida
- Type B sleeves replacing mechanical clamps at a Texas refinery
- Double-hump girth-weld sleeve on a 26-inch Kentucky gas line
- Compression sleeve on a crude line, Middle East operator
- Subsea isolation and permanent bypass after anchor damage on an 8-inch condensate line, Gulf of Thailand
Spotted an error? Engineers keep this site honest.Report an error or suggest a correction